Hi all.
Win98. Project98
I'm relatively new to Project. I've inserted a few project into my main
project, however the inserted tasks are have their durations displayed in
days instead of weeks. The main project has the "durations are entered as
weeks" on the tools/options/schedule tab.. as do the subprojects that i
inserted. so i don't understand why it's showing as days. If it's any help,
I first saved the subprojects with the durations displayed as days, but
changed that before i inserted them into the main project.
i appreciate any help here.
thanks alot
kevin
Win98. Project98
I'm relatively new to Project. I've inserted a few project into my main
project, however the inserted tasks are have their durations displayed in
days instead of weeks. The main project has the "durations are entered as
weeks" on the tools/options/schedule tab.. as do the subprojects that i
inserted. so i don't understand why it's showing as days. If it's any help,
I first saved the subprojects with the durations displayed as days, but
changed that before i inserted them into the main project.
i appreciate any help here.
thanks alot
kevin