P
planthefun
Hi there,
I have a question about the calendar view of a project. Currently,
when in calendar view, in the 'Timescale' menu, if I change the 'Show
week with' option to '5 days', and choose day number index (D1, D2,
D3...) as the display for the Top Row (header), it will still count
the non-working days. I did verify that my project calendar has the
correct days marked as working days.
For example, if 1/1/2008 is the start date of my project, in the
calendar view, I'll see 'D-1' as the header for 12/31/2007, 'D1' for
1/1, 'D2' for 1/2...'D4' for 1/4, then 'D7' for 1/7.
Is there a way for the header to count only working days? Meaning in
the above example, 1/7 would have a header of 'D5', not 'D7'. It does
not have to be in the 'D#' format, as long as it shows day number and
only count working days.
Any pointers are greatly appreciated.
JVan
I have a question about the calendar view of a project. Currently,
when in calendar view, in the 'Timescale' menu, if I change the 'Show
week with' option to '5 days', and choose day number index (D1, D2,
D3...) as the display for the Top Row (header), it will still count
the non-working days. I did verify that my project calendar has the
correct days marked as working days.
For example, if 1/1/2008 is the start date of my project, in the
calendar view, I'll see 'D-1' as the header for 12/31/2007, 'D1' for
1/1, 'D2' for 1/2...'D4' for 1/4, then 'D7' for 1/7.
Is there a way for the header to count only working days? Meaning in
the above example, 1/7 would have a header of 'D5', not 'D7'. It does
not have to be in the 'D#' format, as long as it shows day number and
only count working days.
Any pointers are greatly appreciated.
JVan