A
andypatkinson
Hi
I have a simple set of task that have a parent / summary task.
For some reason that I cannot fathom, when I enter, say 50h, into the
first tasks duration the summary duration shows 100h even though none of
the other tasks have anu hours allocated. It's as if project is
doubling-up on hours for some reason.
Each task has a resource allocated (the same resource) and the tasks
have been made sequential by linking.
I am sure this must be a newbie-style question, but it has me
confused!!
Cheers All
Regards
Andy
I have a simple set of task that have a parent / summary task.
For some reason that I cannot fathom, when I enter, say 50h, into the
first tasks duration the summary duration shows 100h even though none of
the other tasks have anu hours allocated. It's as if project is
doubling-up on hours for some reason.
Each task has a resource allocated (the same resource) and the tasks
have been made sequential by linking.
I am sure this must be a newbie-style question, but it has me
confused!!
Cheers All
Regards
Andy