N
not you
In a Gantt view of my project (MSP2000), when I try to drag the Finish
date of a task, the whole task moves instead of increasing the
Duration. This happens for any task I try to change.
If I create a new task, it behaves the same until I set the Constraint
Type to As Soon As Possible. The task Start date automatically
changes to the Project Start date. Only then I can drag the finish
date to extend the duration.
In a new project file, I can drag the Finish Date as per design.
Help?
Fred
date of a task, the whole task moves instead of increasing the
Duration. This happens for any task I try to change.
If I create a new task, it behaves the same until I set the Constraint
Type to As Soon As Possible. The task Start date automatically
changes to the Project Start date. Only then I can drag the finish
date to extend the duration.
In a new project file, I can drag the Finish Date as per design.
Help?
Fred