Think about why the driveby causes the other task to split. I wouldn't
expect it to be due to a dependency ralationship - those are driven by the
process itself, something you would have known about ahead of time and built
into the schedule from the start (at least you *should* have known about
them). Most, if not all, of the time reason the the driveby would cause
the other task to split would be because it pulls resources off of the
scheduled task. This is a resource leveling issue and the split can be
handled by the leveling process. Give your driveby a higher priority than
the regular task and a SNET constraint so it starts on the day it needs to.
Do NOT link it to the scheduled task. Assign the required resource to it.
The resource will be overallocated due to the conflicting assignment during
the duration of the driveby. Run Leveling with the "Priority, Standard" and
"Leveling can split tasks" options enabled. You'll find the first part of
the scheduled task stays where it was, then there's a split introduced for
the duration of the driveby, then the original task resumes with its finish
pushed out accordingly.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://project.mvps.org/faqs.htm for the FAQs
tz9113 said:
Thanks,
That will help with the recurring tasks. My big problem is with the
non-recurring tasks. For example, I have a five day task, and on day
three, a
new 8 hour "drive by" happens. I want the five day tasks to be interrupted
showing it now becomes a six day task. It seems as though the fixed day
tasks
must be contiguous or at least I have it set that way.
Tom