P
Phillip Armitage
Our office uses MS Project solely for the preparation of presentation GANTT
Charts. That is, once the chart is created, printed out and presented in one
form another it is never refered to in its electronic form again.
When our PM's are putting together a schedule they come up with a list of
tasks, they identify the days they want each task to start and end on, and
that's it. If they feel a particular task should have a duration, they will
refer to a calendar or daytimer to figure out for themselves when the end
date should be.
Is it possible to modify the default settings for MS Project (2002) so that
as I add or modify tasks that I only need enter the start and end dates.
Right now, if I have any task linking going on, I run into situations where
I can't get the end date I desire without playing with a duration value.
Gets really annoying.
Comments? Suggestions?
Charts. That is, once the chart is created, printed out and presented in one
form another it is never refered to in its electronic form again.
When our PM's are putting together a schedule they come up with a list of
tasks, they identify the days they want each task to start and end on, and
that's it. If they feel a particular task should have a duration, they will
refer to a calendar or daytimer to figure out for themselves when the end
date should be.
Is it possible to modify the default settings for MS Project (2002) so that
as I add or modify tasks that I only need enter the start and end dates.
Right now, if I have any task linking going on, I run into situations where
I can't get the end date I desire without playing with a duration value.
Gets really annoying.
Comments? Suggestions?