Steve Scott
A colleague has got a task with two identically named resources allocated to
it at 100% each. How is this possible? If i create two identically named
resources in a new schedule it will not allow me to allocate them both to a
single task.
Also, when my colleague and I try to remove the second resource from the
task (via task dialog bx) it remains there. It can however be removed via
Task usage view.
Are we doing anything wrong or is the file somehow corrupt?
PS - If project does not allow duplicate resources to be allocated why does
this Resource sheet view not prevent this when creating resources?
Thanks in advance
Steve
it at 100% each. How is this possible? If i create two identically named
resources in a new schedule it will not allow me to allocate them both to a
single task.
Also, when my colleague and I try to remove the second resource from the
task (via task dialog bx) it remains there. It can however be removed via
Task usage view.
Are we doing anything wrong or is the file somehow corrupt?
PS - If project does not allow duplicate resources to be allocated why does
this Resource sheet view not prevent this when creating resources?
Thanks in advance
Steve