C
CDAK95
Within my project, I have several resource groups that have different
schedules (i.e. one group work 6.5 hours per day x 5 days, the second group
works 8.5 hours per day x 7 days, and the third group works 10 hours per day
x 7 days). I have set up seperate calendars for each group. However, it
appears the duration is calculated based upon a common calendar. How can I
change this function so it calculates duration based upon the work calendar
specific to each working group?
schedules (i.e. one group work 6.5 hours per day x 5 days, the second group
works 8.5 hours per day x 7 days, and the third group works 10 hours per day
x 7 days). I have set up seperate calendars for each group. However, it
appears the duration is calculated based upon a common calendar. How can I
change this function so it calculates duration based upon the work calendar
specific to each working group?