Hi Jimmy,
We seem to have some definition problems. Tasks are activities which help
towards the completion of the project - what you're calling sub-tasks.
Summaries are not tasks at all in that sense, but just summarise the tasks'
data that are outlined beneath the respective summary. This is more clearly
and diagrammatically explained in my series on Microsoft Project in the
TechTrax ezine, particularly #2 and the section called Outlining, at this
site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site,

Thanks.)
That being said, unless you have more outline levels of summaries within
summaries, each one should not be affected by the others. Is this something
that's just happened? Did you notice the summary totals changing as you
indented to create the summaries? Maybe we have some corruption here. Does
this happen with a new project?
Mike Glen
MS Project MVP