M
maarkr
I thought I was doing OK on putting my project in until....
I have a summary task that shows 57 months to complete.
It has four subtasks...one with two tasks of 5 mos and 1
mo, and the other subtasks for 6 mos and 1 month each.
They all have a start no earlier than date, but if input a
start date for the tasks, it automatically adds 3 weeks
for the finish date. Can this be simply explained...I'm
currently going thru a Que book on project but I'm not
very far yet.
I have a summary task that shows 57 months to complete.
It has four subtasks...one with two tasks of 5 mos and 1
mo, and the other subtasks for 6 mos and 1 month each.
They all have a start no earlier than date, but if input a
start date for the tasks, it automatically adds 3 weeks
for the finish date. Can this be simply explained...I'm
currently going thru a Que book on project but I'm not
very far yet.