E
Erkki Piipari
Hi again
Here's my case:
- a task with work for 2 days and duration equals 2 d
- I change the resources working times for 4 hours or
select a special 4 -hour/day calendar
Here are the results of the finnish jury :
- Start and finish dates change accordingly
- Gantt bar changes ok
- Duration remains 2 d!
MSP help states flatly :
If you have changed the working time in the project
calendar to more or fewer than 8 hours of working time per
day, tasks' durations won't match their Gantt bars.
Is there a fix available for this serious bug?
Should I create a calculated field and code to calculate
correct durations - and bind it to the scheduling engine ?
Maybe someone has done that...
Thanks !
Here's my case:
- a task with work for 2 days and duration equals 2 d
- I change the resources working times for 4 hours or
select a special 4 -hour/day calendar
Here are the results of the finnish jury :
- Start and finish dates change accordingly
- Gantt bar changes ok
- Duration remains 2 d!
MSP help states flatly :
If you have changed the working time in the project
calendar to more or fewer than 8 hours of working time per
day, tasks' durations won't match their Gantt bars.
Is there a fix available for this serious bug?
Should I create a calculated field and code to calculate
correct durations - and bind it to the scheduling engine ?
Maybe someone has done that...
Thanks !