I have created a schedule using the default calendar of 40 hour weeks and 8
hour days.
I have then adjusted the calendar to reflect the standard working time for
our company which is 37.5 hours weeks and 7.5 hours days.
The task bars have now all been slightly adjusted. For example I have a 10
day task that finishes a few hours before the end of the 10th day. So the
succeeding task starts a few hours earlier.
Anyone got any idea on how I might fix this?