Hi all,
I have a quick question (hopefully). Currently using project 2000, use
Fixed Work, effort driven settings and have the following problem:
I have 1 task which I set the fixed work at 10days. on the 1st cut I assign
2 resources at 100% which brings the duration down to 5 days, which is
correct. However after refining I change one of the assigned resource
allocation from 100% to 50% expecting the duration to change from 5d to 7.5d,
however I end up with 10d?
Having tried different variations I get increasingly strange results. The
same situation occurs with the fix units, effort driven settings????
I would be grateful of any help or advice.
I have a quick question (hopefully). Currently using project 2000, use
Fixed Work, effort driven settings and have the following problem:
I have 1 task which I set the fixed work at 10days. on the 1st cut I assign
2 resources at 100% which brings the duration down to 5 days, which is
correct. However after refining I change one of the assigned resource
allocation from 100% to 50% expecting the duration to change from 5d to 7.5d,
however I end up with 10d?
Having tried different variations I get increasingly strange results. The
same situation occurs with the fix units, effort driven settings????
I would be grateful of any help or advice.