Duration not changing

S

Saadia

When a task is completed before the deadline schedules shouldn't the total
duration
on the job change? 3 of my tasks were completed well in advance of their
deadline..
but my duration did not change at all. I used the % complete arror in my
gantt view to show how much of a job was completed.
Any help would be really appreciated.
Thanks
 
J

Jan De Messemaeker

Hi,

When you tell Project a job is 100% complete it doesn't have a clue when it
was completed so yiut takeds teh planned finish date.
How would it know?
You could enter actual duration or once it is 100% complete simply change
duration.
HTH
 
S

Saadia

Hi,
Thanks for your reply.
I tried chaning the duration of the task to the actual duration
it took, but the total duration of the job did still not change.
 
J

Jan De Messemaeker

Hi,

I don't understand, sorry.
Could you specify the exact steps?
For instance:
- First entered 100%
Then entered duration
Or then enterd actual duration...
 
S

Saadia

Hi,
Well i figured out what I was doing wrong. I guess I needed to add the date
the task was completed in the actual finish date area.

Thanks for your help.
 