JS said:
I save the original schedule as a baseline. How do I accomoadate the change
if the actual work done is 7 hours in 5 days? If I enter 7 hours, the task is
automatically stretched to 7 days.
JS,
Jim may have answered your question but I'm not sure it came across.
First, even though a task is fixed duration, that duration MAY change if
additional work is added (contrary to Jim's first paragraph). It all
depends on HOW that work is added. For example, you said that when you
entered actual work of 7 hours the duration increased. That is because
you entered actual work directly into the Actual Work field. The task,
whether baselined or not, was originally scheduled for 5 hours. With the
fixed duration of 5 days, that means Project scheduled the work to be
done 1 hour/day for 5 days. By entering 7 hours into the Actual Work
field you effectively said there are two more hours of work added and at
a scheduled rate of 1 hour/day, that means it will take 7 days. Make
sense? Kind of?
On the other hand, if you had entered actual work on a day by day basis,
for example into the timescaled values for Actual Work on the Resource
Usage view, you could have entered a total of 7 hours of actual work and
the duration would still have remained at 5 days.
The best advice I can give is to go to the Project help file and search
for the "work equation". That tells how the various parts of Project's
work equation interact given the task type.
John
Project MVP