Your question seems a bit confusing to me. Please clarify if my comments
below do not answer your question.
Assumption: On any specific day in the 30 day project, you want to calculate
how much of your project duration is behidnd you. So, on the third work day
you are 3/30=10% Duration Complete.
How to: Insert a task of 30 days duration. Set a status date
(Project/Project Information....). Now status the single task,
Tools/Tracking/Update Project... and set it to only update the one task.
Update the status to the current date (it is an obvious choice).
Why this is a bad idea: Adding tasks to the scheudle for this purpose only
will pollute the overall %Complete of the project. You should only have
measurable tasks (not book keeping tasks) in you schedule.
To consider: Read about Hammock tasks , see FAQ#19. This will let you tie
the "Program Managment Task" to the first and last milestones of the program.
This way, the task will automatically change duration (and %Complete) as the
program duration changes.
Why not use a hand held calculator?
--
If this post was helpful, please consider rating it.
Jim
Visit
http://project.mvps.org/ for FAQs and more information
about Microsoft Project