R
Reb T
Hi all!
Getting very frustrated with project and time calculation.
Doing my marketing plan in it.
I need to achieve the following:
- different campaigns need to be listed and I need to specify the duration
eg. 1/1/06-3/3/06 (I used start and finish day and it keeps telling me that
this is not best practice- WHY)
- within that I need to have subtasks that are within that period but not
necessarily dependent (I know otherwise I can use lag time)
- I need to show each resource's workload in a certain timeperiod ( they
are only helpers and have work of their own)
I need people to help with some of the things e.g. writing an article but i
want the duration of this process (e.g. press release A) to be 1 week and one
person to spend 4 hours over that week and another person 6 hours- BUT not
all in one day... Project keeps recalculating the duration- I don't want this
as I need the time span to stay fixed
What is best practise when:
A I know the time period a task is to happen (with subtasks)
B Resources need to be assigned but don't spend all their time on the task-
only 15% a day and I know how long it would take them to complete their part
of the task e.g. 4 hours.
Can anyone help?
Much appreciated!!!
Getting very frustrated with project and time calculation.
Doing my marketing plan in it.
I need to achieve the following:
- different campaigns need to be listed and I need to specify the duration
eg. 1/1/06-3/3/06 (I used start and finish day and it keeps telling me that
this is not best practice- WHY)
- within that I need to have subtasks that are within that period but not
necessarily dependent (I know otherwise I can use lag time)
- I need to show each resource's workload in a certain timeperiod ( they
are only helpers and have work of their own)
I need people to help with some of the things e.g. writing an article but i
want the duration of this process (e.g. press release A) to be 1 week and one
person to spend 4 hours over that week and another person 6 hours- BUT not
all in one day... Project keeps recalculating the duration- I don't want this
as I need the time span to stay fixed
What is best practise when:
A I know the time period a task is to happen (with subtasks)
B Resources need to be assigned but don't spend all their time on the task-
only 15% a day and I know how long it would take them to complete their part
of the task e.g. 4 hours.
Can anyone help?
Much appreciated!!!