K
Katherine
I typed in some tasks, and I also typed in the resource, amount of work (not
duration), and in some cases the units(ie 50%). I also have selected 'Fixed
Work'.
There are a number of inconsistent things happening as follows:
1) For some tasks, the duration is correct for the units, but has a ? after
it.
2) In some summary tasks, there is a ? after the duration. This seems to be
true If one of the tasks it is summarizing has a ?
duration), and in some cases the units(ie 50%). I also have selected 'Fixed
Work'.
There are a number of inconsistent things happening as follows:
1) For some tasks, the duration is correct for the units, but has a ? after
it.
2) In some summary tasks, there is a ? after the duration. This seems to be
true If one of the tasks it is summarizing has a ?