D
Duncan
I am fairly certain I have done this before, but I am really drawing a blank
for some reason....
MS Project 2003 (SP2)
I need to show a colum that shows days planned to be worked on a set of
tasks - not the calendar time it is going to take to complete it.
For example:
There are 3 tasks in a group of tasks. They each take 2 days to complete.
BUT... the third tasks is delayed to start 5 weeks hence due to a
predecessor. I want a column that shows "6 days" - the actual work planned
to be executed on a task - not "31 days" since the 5 week delay gets included
in the task summary row.
A wrinkle in this would be if two of the three tasks were occuring on the
same days - could I show 6 days or 4 days or both?
I went through a bunch of the columns that I could insert, but nothing
seemed to work.
I may be overthinking this and it may be simple, but I am at a loss....
Thanks!
for some reason....
MS Project 2003 (SP2)
I need to show a colum that shows days planned to be worked on a set of
tasks - not the calendar time it is going to take to complete it.
For example:
There are 3 tasks in a group of tasks. They each take 2 days to complete.
BUT... the third tasks is delayed to start 5 weeks hence due to a
predecessor. I want a column that shows "6 days" - the actual work planned
to be executed on a task - not "31 days" since the 5 week delay gets included
in the task summary row.
A wrinkle in this would be if two of the three tasks were occuring on the
same days - could I show 6 days or 4 days or both?
I went through a bunch of the columns that I could insert, but nothing
seemed to work.
I may be overthinking this and it may be simple, but I am at a loss....
Thanks!