P
Phanindra
HI,
I have two tasks.
I have multiple tasks, i am getting the duration of the tasks but i want to
sum all the sub tasks and show the sum of the days at main task level, which
field i have to use?
Ex:
one task - 20-May-2010 to 25-May-2010 - 5 days
two task - 21-May-2010 to 28-May-2010 - 6 days.
I want to show 5 + 6 = 11 days in a new column at Upper task level. How to
do that.
I have two tasks.
I have multiple tasks, i am getting the duration of the tasks but i want to
sum all the sub tasks and show the sum of the days at main task level, which
field i have to use?
Ex:
one task - 20-May-2010 to 25-May-2010 - 5 days
two task - 21-May-2010 to 28-May-2010 - 6 days.
I want to show 5 + 6 = 11 days in a new column at Upper task level. How to
do that.