"EAC" sometimes not equal to "Cost"

G

g.popken

Hi there,

I'm managing a project server instance with approx. 50 projects and
about 500 resources.


Today I noticed that for some of the projects the EAC is not equal to
the Cost. For all I know this should be!
The difference shows in the project center views as well as in the
project file itself.


In this projectfile all tasks are completed (% complete = % work
complete = 100%).
No remaining work nor cost.
The Baseline cost = Actual Cost = Cost.
The EAC of 5 tasks (of a total of 250) is 20% larger and sometimes 40%

smaller than the Cost.
There's no fixed cost.


any ideas?
 