Earned Value Analysis--Physical % Complete Values

T

Tim from Minnesota

,For some reason, in Project Standard 2003 I can not get the task physical
percent complete fields to consistently roll-up to the sub-summary or project
summary levels. Does any one know how to consistently do this?
 
J

JulieS

Hi Tim,

The Physical % Complete field is an entered field, not a calculated field.
To the best of my knowledge, it doesn't roll up to any summary task, either
consistently or inconsistently.

Hope this helps. Let us know how you get along.

Julie
 
G

Gérard Ducouret

Hello Tim,
You can't, (without any personal formula)
The only use of the Physical % Complete is to alter the calculation of the
BCWP if you allowed this in Tools / Options / Calculation / Earned value /
Default Earned value method : Physical % Complete.
This BCWP will roll-up to the sub-summary or project !

Gérard Ducouret

"Tim from Minnesota" <Tim from (e-mail address removed)> a écrit
dans le message de
news:[email protected]...
 