On Mar 25, 2:07 pm, "Steve House" <
[email protected]>
wrote:
I don't see how it's possible to doearned valueat all without assigning
resources and tracking work hours. I say 'assigning resources' because
work
doesn't exist without an instrument doing it. The SPI is defined as
the
ratio between BCWP and BCWS, Budgeted Cost of WORK Performed to the
Budgeted
Cost of WORK Scheduled. If you don't really need to track costs you
can
still calculate the SPI by arbitrarily assigning a rate of $1.00 per
hour
and calculateEarned Valuebased on what is really Work Hours rather than
Work Dollars but without considering the amount of work hours you
simply
have nothing to calculate with. Duration doesn't do it sinceEarned
Value
is a measure of how much work you got accomplished within a given
duration
compared to the amount of work you should have done within the same
duration. So unless there is either unscheduled non-working time where
no
activity takes place once the project is underway or the original
duration
was overestimated, SPI calculated using duration will always be 1.0 at
all
status dates. Using duration you could end up with a SPI < 1 even when
you're ahead of schedule or even worse, an SPI > 1 when you're really
behind
schedule!
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visithttp://
www.mvps.org/project/faqs.htmfortheFAQs
Hi Everyone - Thank you so much for the time you took to help me out
on this. It has been my experiencing trying to do this that I need
work and that what you posted it absolutely true. What has been
happening with the customer is that they are entering actuals and thus
taking control from what MSP does best. This has created a lot of
issues in the plan and reporting. i will need to consult with the
customer and see how we can minimally get generic resoruces assigned
with a standard rate and then assign work based on an 8 hour day.
Hopefully they will see the light in this and your comments will
help.
I also am considering inputting standard rates in my global that are
not based on firm data (ie, assign all resources at a $50/hour
standard rate). This will allow me to get the EV into the system and
start to show mgmt how it works. has anyone had any experience trying
to get EV into the organization in this manner?
Thank you ALL again - most helpful
K
Ray,
First of all, you're welcome and thanks for the feedback.
Here's a little history behind my initial response. At the company where
I worked, we used Project as the planning and schedule tracking tool but
another system (MPM) to calculateearned value(EV) metrics. For our
needs, the plan was developed and baselined in Project and that data was
then uploaded to MPM. Each month, cost account managers entered
completion data for each task into their Project plan. That data was
then uploaded and used to calculate EV metrics using ACWP from our
financial system. So there are a couple of ways to look at what your
customer is doing. On the surface it appears they don't understand how
Project works and are basically defeating Project's EV functionality. On
the other hand, if they are really using a more precise method of
measuring actuals (i.e. ACWP from the company financial system), then
perhaps they are doing something similar to what we did.
You can use a generic rate of $50 per hour but $1 per hour works just as
well. Some users use this method to "hide" their true rate data from
customers, vendors, etc. while still being able to calculate EV metrics.
Hope this helps.
John
Project MVP- Hide quoted text -
- Show quoted text -