A
Antartica Solutions - Lars Hallin
Hi All,
Been gone from the MSP world for a while and now it's time to get back and
up to date. I remember (incorrectly?) that it used to be possible to edit
the values in the "Actual Cost" column, to diplay a) how much money has been
spent and b) how much remains to be spent as a consequense of f.i. a delay.
I want to update the plan with $ spent and % complete, and not having to
touch the "Total Cost" coulmn.
Probably a one-line answer to this?
Cheeers
Lars
Been gone from the MSP world for a while and now it's time to get back and
up to date. I remember (incorrectly?) that it used to be possible to edit
the values in the "Actual Cost" column, to diplay a) how much money has been
spent and b) how much remains to be spent as a consequense of f.i. a delay.
I want to update the plan with $ spent and % complete, and not having to
touch the "Total Cost" coulmn.
Probably a one-line answer to this?
Cheeers
Lars