No no no - during tracking project needs to change the duration, start
date,
etc, for a task as shown in the plan to be equal to actual performance so
that you can see the "ripple down" effects of variances on future tasks
and
project completion. If I have a critical task that starts a month later
than planned and then also takes a month longer to complete than
originally
expected, it will finish two months later than planned and since it is a
critical task, that absolutely positively means that the project itself
is
going to finish at least 2 months late unless we take corrective action
somewhere in the portion of the project that is still to come. When
tracking, project's job is to continually update the plan to show you the
date you'll hit NOW if things continue on the same path and help you
forge a
remediation strategy by showing you the impact on the project finish of
the
various management decisions you might implement. If you save a baseline
before starting work, it remains static while the plan changes
dynamically.
You use the baseline and the current schedule together to compare the
plan
as it was expected to unfold THEN to what has actually happened until NOW
so
you can accurately predict and control what is going to happen in the
FUTURE. To do that successfully you simply must let the calculating
engine
do its job. Otherwise you're using Project as nothing more than a
glorified
typewriter for Gantt charts.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
On Tools/Options/Calculation deselect "updating task status updates
resource status". This will help you somewhat in separating duration,
effort and completion, though there are some more quirks. Especially
you need to find out a strict sequence in updating the variables. To
keep this simple, I would also strongly recommend switching from
automatic calculation and levelling to manual.
Note that there are three different %complete that you can map to the
sides of the iron triangle: "%complete" maps to time/duration;
"%workcomplete" maps to effort/cost/timecardhours and finally
"%physical complete" maps to scope/delivery. You will want to switch
your earned value method to "physical % complete" and adjust the
default views a bit to completely configure the separate tracking.
As far as the basic MSP formula work=units*duration goes - yes, it's
simple to understand and yes MSP wants to stick to it. Makes sense for
planning, but not for tracking: it's exactly comparing the estimate of
the planning phase (where the formula must be active) preserved in the
baseline with reality (where the formula should only be active when
reality exactly follows plan) - so me too, I like to configure MSP in a
way that allows me to see the difference between plan and actual.
joergn said:
Hi experts
A colleague has the following problem:
"I need duration, effort and %work complete to be independent of each
other but can't seem to get it to behave. For example, I want to be
able to say that a task is 10days effort over a 20 day duration and is
40% complete (without having Resources entered). I then want to be able
to change any of these without the other being impacted. Also if I
enter the resources the percentage completed changes. I don't know of
any solution. Do you?
Looking at the project plan summarized tasks I also realized that the
amount summed up for effort is not the sum of the subtasks. "
I have no clue. Can you help?
Thanks a lot
Jörg