S
Shahriar N k
Hi.
I have a large project where several resources work simultaneously.
The task are in groups, ie. a Summary task with several subtasks and the
(sub)tasks are of different durations.
Now, in a summary task, the subtasks may be performed by different
resources. When performed by different resources the tasks are independent(ie
they can occour/progress simultaneously/independently).
What i would like is:
Lets say R1 has 8hrs of task(/duration) in one day and R2 only 6hrs duration
(in a 8hr work day). I want R1 and R2 to work independently and always
complete 8hr duration of tasks (even if the tasks are taken from different
Summary Tasks).
So, how can I link the tasks(or what else can i do) to achive this?
Thank you.
I have a large project where several resources work simultaneously.
The task are in groups, ie. a Summary task with several subtasks and the
(sub)tasks are of different durations.
Now, in a summary task, the subtasks may be performed by different
resources. When performed by different resources the tasks are independent(ie
they can occour/progress simultaneously/independently).
What i would like is:
Lets say R1 has 8hrs of task(/duration) in one day and R2 only 6hrs duration
(in a 8hr work day). I want R1 and R2 to work independently and always
complete 8hr duration of tasks (even if the tasks are taken from different
Summary Tasks).
So, how can I link the tasks(or what else can i do) to achive this?
Thank you.