Empty fields on the subproject's summary task from the master proj

E

EDMRNK

Using Microsoft Project 2002, somehow on the Master Project the SPI, CPI and
Baseline Start and Finish dates are shown with no values on the subproject’s
summary task. If I open the subprojects isolatedly (not in the master
project), these fields are correctly shown on the project summary task with
the correct values. Is that a problem of MSP 2002 with inserted projects to a
master project?
 
E

EDMRNK

Rod, thanks for your reply, but what makes me think that it should work is
that I have several past programs using this feature with MSP 2003 PRO, that
at least populated the Baseline Start and Finish dates on the master project
correctly, but even this simple feature is not working in the present program
using MSP 2002. But I’m not sure about MSP’s SPI and CPI fields because I
used customized calculated fields for both indicators in the subprojects in
the past programs with MSP 2003 PRO. Unfortunately at my present company we
use MSP 2002 Server/Pro version, and I guess that perhaps there’s something
wrong with some configuration option, or simply a bug in MSP 2002.
 