E
EDMRNK
Using Microsoft Project 2002, somehow on the Master Project the SPI, CPI and
Baseline Start and Finish dates are shown with no values on the subproject’s
summary task. If I open the subprojects isolatedly (not in the master
project), these fields are correctly shown on the project summary task with
the correct values. Is that a problem of MSP 2002 with inserted projects to a
master project?
Baseline Start and Finish dates are shown with no values on the subproject’s
summary task. If I open the subprojects isolatedly (not in the master
project), these fields are correctly shown on the project summary task with
the correct values. Is that a problem of MSP 2002 with inserted projects to a
master project?