Hii,
Indeed, you cannot change a task to be recurring.
You create it through Insert, recurring task.
HTH
--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs:
http://www.mvps.org/project/faqs.htm
"Mary" <
[email protected]> schreef in bericht
I'm sorry - but where in the task information screen do I set that... I
don't
see the option of setting the task as reoccurring and where I can specify
the
day of the week (and time) the meeting takes place. (Do I need to expand
the
columns that appear in the Gantt view? If so, what columns?)
:
You enter it as a recurring task, duration of 2 hours, recurring weekly
on
Monday starting at whatever time the meeting is held and continuing for
40
weeks.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
Is there a way to enter a weekly task in one line item... for example,
if
there is a weekly status meeting every Monday for 2 hours over the
course
of
10 months, how can you ensure the resources time is allocated for
those 2
hours each Monday w/o having to enter multiple tasks (i.e. one for
each
week.)