You can stop it from updating the % complete in response to entering actual
work by going to the Tools menu, Options, item, and selecting the
Calculation tab and deselecting the first check box that says "Updating task
status updates resource status." But before you do, think it over and make
sure you really want to. If I have a task that requires 5 days to complete
with a resource assigned to it 100% it requires 40 man-hours of work. If my
resource does 8 hours work, he has done 1/5 of the task's required effort as
evidenced by producing 1/5 of the number of widgets the task is required to
produce and if he's working at the rate I thought he would he's spent 1/5 of
the time I'd figured it would take him to do it. The duration of the task
is 5 days, actual duration is 1 day, remaining duration is 4 days, task is
20% complete. If he's done 8 hours work and only made 1/10 of the required
widgets, my estimate of duration and work was off and should be revised to
reflect that it will require 10 days, not 5, to make all the widgets. I
post 8 hours actual work, actual duration is set to 1 day, I manually set
remaining duration to 9 days, task is calculated at 10% complete because
he's worked 1 day out of the total of 10 days it will require to do the
work.
DO NOT "MIX AND MATCH" TIME HOURS AND WORK HOURS!!! They are NOT the same
thing even though they both use the same unit of measure and they cannot be
freely interchanged with each other in the same fields. Be careful not to
mix them up accidentally or from expediency, either in the schedule or in
your own mind. I can't stress that strongly enough.
Project's schedule shows projected work and expected duration for things
that haven't happened, actual work and expended duration for things that
have happened. As such, it should normally be allowed to update duration
and % complete in order to best use the schedule as an effective management
tool. % complete is expended duration / required duration, if you need to
know percentage of the *work* that has been done, that's % Work Complete, a
different field altogether. % Complete and % Work Complete are not always
equal even though they often are. Remember too that there are Actual XX
fields corresponding to each "scheduled" field and that's where you post
what has happened - updating Actual Start will update Start and updating
Actual Duration can update duration but it's a one-way street and changing
the Start date or Duration field is NOT how you enter actual progress. So
how do you preserve your original estimates for comparison purposes, which
is what I think you are trying to do by wanting to turn off the updating?
After developing your projected schedule but before posting any actual
performance in it, save a baseline. That replicates the data fields into
baseline pigeon holes where they are protected against change. So in the
above example. The original plan shows 5 days duration, 40 hours work.
Saving a baseline copies that to the corresponding baseline fields. Now Joe
does 8 hours work and tells you he estimates that he'll be finished in 3
more days, not the 4 that was originally expected. You enter 8 hours in
Actual Work and Project updates Actual Duration to 1 day, you enter
Remaining Duration of 3 days, Project revises the total work estimate to 32
hours and the total duration estimate to 4 days - of which you have so far
worked one day - and the task is 25% complete. Meanwhile your baseline
retains the 5 day duration and the 40 hours work from your original
estimates so you have a record of that data to compare actual progress
against.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs