Hi Ian,
Well, there is nothing wrong with the method you describe.
You should be able to enter Actual Work for any time you wish -
before
or after the task was originally scheduled (baselined).
Just to check, you note you are using Project 2003. Are you using
2003
Professional or 2003 Standard? Project Professional does have an
[Actual Work Protected] field that will not allow manual data entry.
Let us know.
Julie
IanDavison said:
Hi Julie,
To enter 'actuals' data I use the View menu to bring up the task
usage
sheet. In the 'Details' column I right click the mouse to show the
'Act W'
rows. The figures in the @Work' row finish on 27/3. When I try to
enter an
'Act W' figure for 01/05 the screen won't accept any data. No error
messages
are shown. I assume that it is because I am trying to enter data
after
the
end date of the planned work in the Gannt chart.
:
Hi Ian,
I assume by saying to want to enter "actuals" in May, you are
talking
about Actual work in the Task Usage view. I assume you are
showing
Actual Work in the timescaled (right side) portion and attempting
to
add
Actual Work to tasks? Can you give a bit more information around
"it
does not allow me" -- what error messages if any are you seeing?
What
are you attempting to do?
Julie
message
I have a MS Project 2003 baselined plan. On 1 particular entry
the
activity
was meant to be completed by the end of March. It is currently
showing
as 80%
complete. Due to circumstances beyond my control I now want to
enter
some
'actual' data against it in May but it does not allow me to
enter
data
when I
try using the task usage screen. Any ideas please?
Thanks in advance.