S
sbfilm
Hi,
I am using Project 2007 and I am attempting to enter specific start and
finish dates and times in the task information dialog box. For example,
I am trying to make create a task that begins on January 21, 2009 at
5:30 PM and ends on January 21, 2009 at 7:30 PM. However, after I enter
the information and click "ok" the times and dates inexplicably change.
Does anyone know what the problem here is?
Thanks in advance for any help.
I am using Project 2007 and I am attempting to enter specific start and
finish dates and times in the task information dialog box. For example,
I am trying to make create a task that begins on January 21, 2009 at
5:30 PM and ends on January 21, 2009 at 7:30 PM. However, after I enter
the information and click "ok" the times and dates inexplicably change.
Does anyone know what the problem here is?
Thanks in advance for any help.