M
Mark
The "Baseline Work" summary level field does not increment
when a new task is added and the task work baselined. It
appears the summary level "Baseline Work" only updates if
you re-baseline the summary task, which is not acceptable
since this resets the summary baseline start, finish, etc.
fields.
Is there a way to change the way the summary level rolls
up the baseline work field (i.e. sums the task baseline
work)?
Thanks for your assistance.
when a new task is added and the task work baselined. It
appears the summary level "Baseline Work" only updates if
you re-baseline the summary task, which is not acceptable
since this resets the summary baseline start, finish, etc.
fields.
Is there a way to change the way the summary level rolls
up the baseline work field (i.e. sums the task baseline
work)?
Thanks for your assistance.