A
andrewandrew
Is there a way that I can assign a work resource to a task without increasing
the work (worker-hours) of that task? For example, say there is only one
crane on a large industrial project. It is important to be able to use
resource-levelling tools for that crane, so that it's not scheduled to be in
two places at once, so I want to assign the crane to tasks as a work
resource. Say the crane is necessary on an 8 hour task that has three workers
assigned to it, for a total of 24 worker-hours. When I assign the crane and
keep the duration the same, the work calculation includes the crane for a
total of 32 hours. How can I exclude the crane from the work calculation,
while still taking advantage of load levelling, max units, and resource
over-allocation functionality?
Andrew
the work (worker-hours) of that task? For example, say there is only one
crane on a large industrial project. It is important to be able to use
resource-levelling tools for that crane, so that it's not scheduled to be in
two places at once, so I want to assign the crane to tasks as a work
resource. Say the crane is necessary on an 8 hour task that has three workers
assigned to it, for a total of 24 worker-hours. When I assign the crane and
keep the duration the same, the work calculation includes the crane for a
total of 32 hours. How can I exclude the crane from the work calculation,
while still taking advantage of load levelling, max units, and resource
over-allocation functionality?
Andrew