I
inay
Hello
I am developing a schedule for a series of events (part of a conference).
The start date/delivery of the events can not move. I want to be able to set
dependencies such that:
- the event start/finish dates do not move;
- any other tasks that directly impact the delivery of the event are linked
such that should slippages in these events cause the start date of an event
to be jeapordised, the lead up activities will flag as red (understand that I
can set the CP to show as red, are there other flag/indicators avaialble?);
- i can manage the critical path and view the changes in slack for tasks on
the CP;
- once we are using the tracking gannt, i can use project to reschedule all
other tasks, other than the actual events themselves, if there are slippages.
I've researched past posts and am trying to work out the best approach.
Should I:
- create links between critical path activities to the events and set
negative lags (I've started to do this, however, am finding it doesn't give
me the flexibility to start tasks sooner than the lastest dates required);
- use deadlines (havent' really used these in the past so don't know how
this will 'flag' slippages and the critical path)
- set must finish on constraints (but my understanding from others is that
this is not optimal as it may not enable me to make use of project's ability
to reschedule tasks down the line)
Thanks - it's a long one!
I am developing a schedule for a series of events (part of a conference).
The start date/delivery of the events can not move. I want to be able to set
dependencies such that:
- the event start/finish dates do not move;
- any other tasks that directly impact the delivery of the event are linked
such that should slippages in these events cause the start date of an event
to be jeapordised, the lead up activities will flag as red (understand that I
can set the CP to show as red, are there other flag/indicators avaialble?);
- i can manage the critical path and view the changes in slack for tasks on
the CP;
- once we are using the tracking gannt, i can use project to reschedule all
other tasks, other than the actual events themselves, if there are slippages.
I've researched past posts and am trying to work out the best approach.
Should I:
- create links between critical path activities to the events and set
negative lags (I've started to do this, however, am finding it doesn't give
me the flexibility to start tasks sooner than the lastest dates required);
- use deadlines (havent' really used these in the past so don't know how
this will 'flag' slippages and the critical path)
- set must finish on constraints (but my understanding from others is that
this is not optimal as it may not enable me to make use of project's ability
to reschedule tasks down the line)
Thanks - it's a long one!