Nicolas
How can I export (e.g. to excel) the start/finish TIMES that MS project calculates automatically (based on dependencies, the calendar settings etc). I know how to export the start/finish dates : choosing the "microsoft project field" called "start" and "finish", but there is no such field for the start/finish times (e.g. at what time during the day is a task planned to start and stop). Is it possible to get those times exported, next to the dates ?