I tried to create a table to export all of the task fields to Excel. I began
at the top and only got to Start9.

I need to do this for a couple of reasons:

1. Rebuild the file as allast resport to fixing a corrupted project file

2. Rebuild the file because I want to decouple all of the resources to a
resource pool and start over.

Thanks in advance for the help

Stretch
 
J

JackD

Rebuilding the file from an excel file may not restore the timescaled data
(things like actual work or contoured work assignments) - it is better to
just save a back-up in case of corruption.

I don't use resource pools, but isn't there already a command to disconnect
from the resource pool already?
 
S

Stretch

Jack,

Thanks for responding

I was remiss - I forgot to mention that I am using Proj 2002 Standard..

I'm not aware of a command to disconnect from the resource pool. Do you
know what the command is?

TIA,

Stretch
 