Lone
I'm trying to change the pathnames of links to external
tasks (as the path changed due to some other problems),
but the pathnames for external predecessorsexceed the
field length and a "..." appears at the end. I've tried to
export the field to Excel, but the "..." still appears.
I have also tried using the task information dialog box,
but I cannot change the path, as the predecessors field in
there are grey and not editable.
Is there any way I can change the length of the
predecessors field without using VBA as I'm not compentent
in using that.
thanks in advance
tasks (as the path changed due to some other problems),
but the pathnames for external predecessorsexceed the
field length and a "..." appears at the end. I've tried to
export the field to Excel, but the "..." still appears.
I have also tried using the task information dialog box,
but I cannot change the path, as the predecessors field in
there are grey and not editable.
Is there any way I can change the length of the
predecessors field without using VBA as I'm not compentent
in using that.
thanks in advance