C
Christa
Hello, glad to find this board.
I am trying to display a few kinds of tasks in the calendar view: one
resource plus some milestones that have no resource assigned to it (such as
client submissions, client feedback expected, etc). The goal is to have a
calendar for each resource that shows their own tasks PLUS some major common
milestones. Applying the "Using Resrouce" filter does almost what i want but
I don't know how get the client submission milestones on there. I was
thinking I could create a new resource called "submissions" and then try to
filter for 2 resources in calendar view, but I can't see how to filter for
more than one resource. (Actually for a different purpose I would like to be
able to filter for more than one resource - would that be done using resource
groups??)
There might be something useful in reports but since I don't have a printer
connection this function is not available to me. Also, I'm running Project
through Virtual PC on a Mac (creative company!!) and there are many inherent
printing problems.
Any suggestions to filter either by multiple resources OR showing a resource
+ certain other tasks?
Many thanks,
Christa
I am trying to display a few kinds of tasks in the calendar view: one
resource plus some milestones that have no resource assigned to it (such as
client submissions, client feedback expected, etc). The goal is to have a
calendar for each resource that shows their own tasks PLUS some major common
milestones. Applying the "Using Resrouce" filter does almost what i want but
I don't know how get the client submission milestones on there. I was
thinking I could create a new resource called "submissions" and then try to
filter for 2 resources in calendar view, but I can't see how to filter for
more than one resource. (Actually for a different purpose I would like to be
able to filter for more than one resource - would that be done using resource
groups??)
There might be something useful in reports but since I don't have a printer
connection this function is not available to me. Also, I'm running Project
through Virtual PC on a Mac (creative company!!) and there are many inherent
printing problems.
Any suggestions to filter either by multiple resources OR showing a resource
+ certain other tasks?
Many thanks,
Christa