Filter in resource usage for different rates

E

emmapso

I have a project plan that includes tasks chargeable to the customer and
tasks that are not.

I understand that I can set these up as a rate table (I've found
instructions on this via this group). But I need to provide a view of the
resource usage split out by person and then there chargeable & non chargeable
time. Is this possible?

Thanks,

Emma
 
J

Jan De Messemaeker

Hi,

Use the grouping feature on Resource Name, then Cost Rate Table
(Wil only work properly on P2002 and >)
 
E

emmapso

Hi

Thanks for this, it's nearly there but the problem I have is on our reports
we only look at the summary against the resource name i.e. all the rolled up
activities.
We take this by week and then enter into a resource profile we keep
elsewhere. By using the 'group by' the tasks are only for Cost rate table A
or B, but the summary line is still the total for both. Is there anyway to
get round this?

Emma
 
J

Jan De Messemaeker

????? If there is a grouping within the task for Cost rate table A, that
subgroup has a "group summary line" hasn't it? And the values in that line
are only fo A???
 