Hi,

The filter Incomplete tasks has two criteria % complete <> 100% OR % work
complete <> 100%.

Why is it necessary to have those two conditions. Is % complete not
sufficient?

Thanks.
 
J

Jan De Messemaeker

Dag Peter,

I never thought about this but yes, there is a way to have a task (be it a
summary task) have work complete but not duration
Make a summary with 2 subtasks
Assign any resource to Task 1
No resource on 2
Now put 1 to 100% complete
Look at both % complet for the summary task.

There may be more combinations...