Filter Task Not complete for which predecessors have been complete

Y

yann

Dear all,

I would like to force user to be able to update tasks for which only if
their predecessors have been completed 100% (in this case preventing for a
task to be completed before its predecessors has been completed).
Is there any way, maybe on a particular filter on PWA my tasks or should i
go on native in Microsoft Project Plan?
Thanks for your help,
 
R

Rod Gill

You will need VBA or PSI code to do this. Project and Project Server only
filter based on data for one task at a time, so they cannot filter on a task
and its predecessors or sub-tasks etc.

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




yann said:
Dear all,

I would like to force user to be able to update tasks for which only if
their predecessors have been completed 100% (in this case preventing for a
task to be completed before its predecessors has been completed).
Is there any way, maybe on a particular filter on PWA my tasks or should i
go on native in Microsoft Project Plan?
Thanks for your help,

__________ Information from ESET Smart Security, version of virus
signature database 5086 (20100504) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 5086 (20100504) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top