Hello SBC,

Thanks for the clarification. I think the wrapping of the text in my reply
to you may have added some confusion. There is a filter called "Using
Resource in Date Range" that I was referring to. But it doesn't sound as if
you are using that filter anyway.

When you say there are "back dated" tasks can you explain more? Is it
possible that the filter you are using a custom filter with additional
criteria defined -- such as task less than 100% complete.

To check: go to Project > Filtered for > More filters. Select the filter
you are applying and see if the Edit button is available. If it is (you can
click on it) view the filter definition and see if there are additional
criteria set. By default the "Using Resource" filter only filters tasks for
a specific resource name, no other criteria are set.

I hope this helps. Let us know how you get along.

Julie
 
J

JulieS

Hello SBC,

I assume you are trying to filter the Gantt chart? Are you certain you are
using the Using Resource... filter and not the Using Resource in Date Range
filter?

I hope this helps. Let us know how you get along.

Julie
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top