W
WSH
I have managed to filter many of the resources on MS Project 2003 by going
onto Project>customise filter and filling out the little table with resource
name, value OR resource name, value etc etc...
I have a task that is assigned to more than one resource and because of
this, it is not filtering this task with the two resources assigned to it.
Question:
How can I filter more than one resource assigned to the same task?
Thank youx
onto Project>customise filter and filling out the little table with resource
name, value OR resource name, value etc etc...
I have a task that is assigned to more than one resource and because of
this, it is not filtering this task with the two resources assigned to it.
Question:
How can I filter more than one resource assigned to the same task?
Thank youx