As a criteria, you can use the "Summary" field which contains "Yes" in front
of summary tasks, and "No" in front of the others ones.
Project / Filetered for / More filters / New...
As a criteria, you can use the "Summary" field which contains "Yes" in front
of summary tasks, and "No" in front of the others ones.
Project / Filetered for / More filters / New...
Or.... you can go to Tools/Options.../View tab and deselect Show summary
tasks.
Mike Glen
MS Project MVP