D
DMW
Can MS Project automatically update the finish date to the date 100%
completion was entered or approved?
completion was entered or approved?
Haris Rashid said:hi,
you can use the "Actual Finish" column, this field shows the date and time
when a task or assignment was actually completed. The Actual Finish field
contains "NA" until there is zero remaining work or you set the task's %
Complete field or the task or assignment's % Work Complete field to 100. When
the work complete reaches 100 percent, Microsoft Office Project sets the
Actual Finish field to the status date or scheduled finish date.
When you specify that a task is 100 percent complete, Project automatically
adjusts the actual finish date based on either the current status date or the
scheduled finish date. The date that is used depends on your calculation
preferences. To examine and set these preferences, click Options on the Tools
menu, and then click the Calculation tab. Based on your calculation
preferences for this project, select or clear the four check boxes starting
with the Move end of completed parts after status date back to status date
check box.
Regards,
Haris
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.