Foxy
Hi, I have read the discussions about FS links and how there cannot be any
date constraints in order for the automatic calculation to work. I have
checked out my tasks and insured that there are no date constraints
(everything is ASAP) and that automatic calculation is turned on. Yet, the
task that I have specified to start when another ends does not get
recalculated to that starting date. It remains where it is, previous to the
starting date.
I have something like:
* Summary Task A
* Summary Task B
* Task 1
* Task 2
* Summary Task C
* Task 3
* Summary Task D
* Summary Task E
* Task 4
I am trying to link Task 3 Finish-to-Start to Task 4. But Task 4 does not
move! Help!
date constraints in order for the automatic calculation to work. I have
checked out my tasks and insured that there are no date constraints
(everything is ASAP) and that automatic calculation is turned on. Yet, the
task that I have specified to start when another ends does not get
recalculated to that starting date. It remains where it is, previous to the
starting date.
I have something like:
* Summary Task A
* Summary Task B
* Task 1
* Task 2
* Summary Task C
* Task 3
* Summary Task D
* Summary Task E
* Task 4
I am trying to link Task 3 Finish-to-Start to Task 4. But Task 4 does not
move! Help!