E
Erkan
Hi,
I have such problem. I'm planning for a project which is a off-town
assignment. the resources (man-thing
) can stay in hotels even the
assigned task is one hour according to the aggreement. However the tasks are
hour-based tasks. I mean if the task is 2 hour (1500US$/day) and the hotel
fee is US$100/day the the daily charge to the client should be
1600US$(=1500US$/hour * 2hours + 100us$/day)
Of course the resource and task number is more than 1
Could you give me any idea about how I can have msProject to make the
calculations?
I have such problem. I'm planning for a project which is a off-town
assignment. the resources (man-thing
assigned task is one hour according to the aggreement. However the tasks are
hour-based tasks. I mean if the task is 2 hour (1500US$/day) and the hotel
fee is US$100/day the the daily charge to the client should be
1600US$(=1500US$/hour * 2hours + 100us$/day)
Of course the resource and task number is more than 1
Could you give me any idea about how I can have msProject to make the
calculations?