C
Cole
Question on something I haven't been able to figure out and it happens
if the task is complete or in progress.
I have set the whole schedule to Fixed Duration but whenever I add or
delete a resource my start and finish dates change.
I thought with type set as Fixed Duration the dates shouldn't change
even if the overall work hours for the task did change.
I know Fixed Work will keep the work the same which should then keep
the date per se in check but I think Fixed Duration will do this job
better until I'm finished resource loading.
Any thoughts?
Cole
if the task is complete or in progress.
I have set the whole schedule to Fixed Duration but whenever I add or
delete a resource my start and finish dates change.
I thought with type set as Fixed Duration the dates shouldn't change
even if the overall work hours for the task did change.
I know Fixed Work will keep the work the same which should then keep
the date per se in check but I think Fixed Duration will do this job
better until I'm finished resource loading.
Any thoughts?
Cole