David
Hi All,
I have a task wich is Fixed duration and not effort driven. The task is 8
days long and I have a few resources assigned to it. When I change the
actual work, the duration increases !
Resource 1, 80%, 16,8 hours Work
Resources 2 to 8, 20%, 1,4 hours Work
When I put in the following Actual Work:
Resource 1, 30 hours AW, 54%, duration still 8 days
Resource 2, 7 hours AW, 13%, duration increases to 15 days !
And the same pattern goes on for resources 3 to 8...
Does anyone have a pointer to give on what's going in my plan ?
Thanks
David
I have a task wich is Fixed duration and not effort driven. The task is 8
days long and I have a few resources assigned to it. When I change the
actual work, the duration increases !
Resource 1, 80%, 16,8 hours Work
Resources 2 to 8, 20%, 1,4 hours Work
When I put in the following Actual Work:
Resource 1, 30 hours AW, 54%, duration still 8 days
Resource 2, 7 hours AW, 13%, duration increases to 15 days !
And the same pattern goes on for resources 3 to 8...
Does anyone have a pointer to give on what's going in my plan ?
Thanks
David