Fixed duration not so fixed

D

David

Hi All,
I have a task wich is Fixed duration and not effort driven. The task is 8
days long and I have a few resources assigned to it. When I change the
actual work, the duration increases !

Resource 1, 80%, 16,8 hours Work
Resources 2 to 8, 20%, 1,4 hours Work

When I put in the following Actual Work:
Resource 1, 30 hours AW, 54%, duration still 8 days
Resource 2, 7 hours AW, 13%, duration increases to 15 days !

And the same pattern goes on for resources 3 to 8...

Does anyone have a pointer to give on what's going in my plan ?

Thanks
David
 
J

JulieS

Hi David,

It's a bit difficult to tell what is going on from your description.

You tell us how much actual work you are entering, but don't tell us how
you are entering the work.

What does the 54% represent -- % complete or % work complete or
assignment units? If Resource 1 has 30 hours of actual work, how can
s/he be 54% complete -- when the original scheduled work was just under
17 hours of work?

Give us a bit more details on your setup (what is your definition of a
"day" for example -- how many working hours -- ), how are you adding the
actual work -- what view, and we'll try to assist.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 
M

Mike Glen

Hi David,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #10 on multiple resource assignments, at this
site: http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top