I have a resource who is working on a single project for an extended period
of time. During that time he will also be working on production issues. So,
I created a fixed duration task and I set his units on that task to approx.
10% (priority was set to 999 as well). When I leveled, I expected that each
day, he would be scheduled for 1 hour of production support and 7 hours of
project work. Instead, Project scheduled 1 hour of production support, but
nothing else. His project time was pushed until after the fixed duration
task ended (2 months later).
How do I get the multiple tasks to be split according to the resource units
for each task?
of time. During that time he will also be working on production issues. So,
I created a fixed duration task and I set his units on that task to approx.
10% (priority was set to 999 as well). When I leveled, I expected that each
day, he would be scheduled for 1 hour of production support and 7 hours of
project work. Instead, Project scheduled 1 hour of production support, but
nothing else. His project time was pushed until after the fixed duration
task ended (2 months later).
How do I get the multiple tasks to be split according to the resource units
for each task?